2nd Street Utilities Relocation Project

Filed under: General,Notices and Advisories — Admin @ 5:44 pm

Project Location

The Morehead Utility Plant Board would like to announce work will begin on a $246,970 utilities relocation of their sewer, water and gas lines.

Crews with ConnHurst Construction Company will start work around August 9, 2010.

Tentative work schedule by contractor:

  • Contract period 120 days
  • Start Date: July 26, 2010
  • Completion Date: October 26, 2010

Motorists should expect delays in this area during the project and should plan their trips accordingly.

Possible road closures

  • Fleming Avenue
  • Allen Avenue
  • Knapp Avenue
  • Church Street

Motorists should expect delays in this area during the project and should plan their trips accordingly.  The traffic changes are necessary so crews can complete the work efficiently and safely.

Barring inclement weather or other delays, the project should be finished by October 31, 2010.

MUPB appreciate your cooperation and patience during this project.